Provide the Project Number. Take care
to enter it exactly. If the project is from a previous system, the screen will
change to look like this:

Select No to change the project number you’ve entered. Select Yes to
proceed.
Select the Inspection Type.
Construction Visits will not grant occupancy to a building. Final Inspections
may. This can be changed by the Inspector at a later date if necessary (if they
are not ready for a Final, for example).
Provide the Requested Inspection Date.
This date must be later than or the same as today’s
date.
Comments. Add any comments that are pertinent for the Inspector to know – for instance, who requested the inspection, who will be on site, etc.